Jack & slide

Where it's the right method

Equipment built for serious weight

01

Survey and engineer the move

We inspect the route, ground, clearances, and manufacturer’s drawings to prepare a safe jack-and-slide plan.

02

Survey and engineer the move

Timber mats, cribbing, jacks, and track are positioned, and the trailer is aligned with the pad.

03

Jack the transformer off the trailer

The transformer is raised evenly using approved jacking points, with cribbing added for continuous support.

04

Build the slide track

Parallel tracks are installed, levelled, and securely supported from beneath the transformer to the pad.

05

Lower onto the skid shoes

Low-friction skid shoes are positioned beneath the base, and the transformer is lowered onto them.

06

Slide in short, controlled strokes

Hydraulic equipment moves the transformer along the track in short, controlled strokes while the crew monitors alignment.

07

Align over the pad

The transformer is guided onto the pad and checked against the marked centerlines for accurate positioning.

08

Jack down onto the foundation

The track and skid shoes are removed, and the transformer is carefully lowered onto the foundation for final inspection.

What the job NEEDS

Information and planning

Lifting and support

Sliding

Have a transformer that a crane can't set? Reach out to us now

Apex Global Heavy Haul & Rigging handles the haul and the set, from the plant to the pad. Dayton, Ohio. USDOT #4560267.